PRMS/SEC Reserves Definitions
Also see
From the Petroleum
Engineering Handbook, at
http://petrowiki.org/Reserves_definitions:
"1P
Equivalent to Proved Reserves
Glossary of Reserves/Resources Terminology - 2005.
Taken to be equivalent to Proved
Reserves; denotes low estimate scenario of Reserves
Glossary of Terms Used in Resources Evaluations - 2007 -
2.2.2.
2P
The Sum of Proved Reserves plus
Probable Reserves
Glossary of Reserves/Resources Terminology - 2005.
Taken to be equivalent to the sum
of Proved plus Probable Reserves; denotes best estimate
scenario of Reserves
Glossary of Terms Used in Resources Evaluations - 2007 -
2.2.2.
3P
The Sum of Proved Reserves plus
Probable Reserves plus Possible Reserves
Glossary of Reserves/Resources Terminology - 2005.
Taken to be equivalent to the sum
of Proved plus Probable plus Possible Reserves; denotes high
estimate scenario of reserves
Glossary of Terms Used in Resources Evaluations - 2007 -
2.2.2.
-
Sub-Classes
-
Reserves are those
quantities of hydrocarbons which are anticipated
to be commercially recovered from known
accumulations from a given date forward under
defines conditions
Glossary of Reserves/Resources Terminology -
2005.
-
Reserves are those
quantities of petroleum anticipated to be
commercially recoverable by application of
development projects to known accumulations from
a given date forward under defined conditions
Table 1: Definition: Recoverable Resources
Classes and Sub-Classes - 2007.
-
Reserves must satisfy
four criteria: they must be discovered,
recoverable, commercial, and remaining based on
the development project(s) applied. Reserves are
further subdivided in accordance with the level
of certainty associated with the estimates and
may be sub-classified based on project maturity
and/or characterized by their development and
production status
Table 1: Guidelines: Recoverable Resources
Classes and Sub-Classes - 2007.
-
To be included in the
Reserves class, a project must be sufficiently
defined to establish its commercial viability.
There must be a reasonable expectation that all
required internal and external approvals will be
forthcoming, and there is evidence of firm
intention to proceed with development within a
reasonable time frame.
-
-
-
A reasonable
time frame for the initiation of
development depends on the specific
circumstances and varies according to
the scope of the project. While 5 years
is recommended as a benchmark, a longer
time frame could be applied where, for
example, development of economic
projects are deferred at the option of
the producer for, among other things,
market-related reasons, or to meet
contractual or strategic objectives. In
all cases, the justification for
classification as Reserves should be
clearly documented.
-
To be included
in the Reserves class, there must be a
high confidence in the commercial
producibility of the reservoir as
supported by actual production or
formation tests. In certain cases,
Reserves may be assigned on the basis of
well logs and/or core analysis that
indicate that the subject reservoir is
hydrocarbon- bearing and is analogous to
reservoirs in the same area that are
producing or have demonstrated the
ability to produce on formation tests."
From the
SEC Petroleum Reserves Definitions:
"PROVED RESERVES (SEC DEFINITIONS)
Securities and Exchange Commission
Regultion S-X Rule 4-10 paragraph (a) defines proved
reserves as follows:
Proved oil and gas reserves.
Proved oil and gas reserves are the estimated quantities of
crude oil, natural gas, and natural gas liquids which
geological and engineering data demonstrate with reasonable
certainty to be recoverable in future years from known
reservoirs under existing economic and operating conditions,
i.e., prices and costs as of the data the estimate is made.
Prices include consideration of changes in existing prices
provided only by contractual arrangements, but not on
escalations based upon future conditions.
...
UNPROVED RESERVES (SPE/WPC
DEFINITIONS)
Unproved
reserves are based on geologic and/or engineering data
similar to that used in estimates of proved reserves; but
technical, contractual, economic, or regulatory
uncertainties preclude such reserves being classified as
proved.
Unproved reserves
may be estimated assuming future economic conditions
different from those prevailing at the time of the estimate.
The effect of possible future improvements in economic
conditions and technological developments can be expressed
by allocating appropriate quantities of reserves to the
probable and possible classifications.
Probable Reserves. Probable
reserves are those unproved reserves which analysis of
geological and engineering data suggests are more likely
than not to be recoverable. In this context, when
probabilistic methods are used, there should be at least a
50 percent probability that the quantities actually
recovered will equal or exceed the sum of estimated proved
plus probable reserves.
...
Possible Reserves. Possible
reserves are those unproved reserves which analysis of
geological and engineering data suggests are less likely to
be recoverable than probable reserves. In this
context, when probabilistic methods are used, there should
be at least a 10 percent probability that the quantities
actually recovered will equal or exceed the sum of estimated
proved plus probable plus possible reserves."
These P90,
P50, and P10 exceedance probabilitiy definitions are correct and rigorous
when robust probabilistic methods are used, but otherwise the 1P,2P, and 3P
definitions become technically incorrect and somewhat arbitrary, and very
confusing. 1P, 2P,
and 3P are low ("proved"), median ("proved plus probable"), and high ("proved
plus probable plus possible") estimates of reserves may
be quantified in probabilistic reservoir modeling (and economics), from
uncertainties in the descriptive and control (and economic) variables, as exceedance
P90, P50, and P10 (or as cumulative P10, P50, and P90) estimates of
reserves, respectively. Commercially-recoverable reserves could be
defined in units of BOE, by some simple value function of production and
injection, or by NPV. The latter is more accurate and
appropriate, as the
definition of what will be "commercially-recoverable" in the future
certainly depends on economics, and is specifically indicated by NPV > 0, but it introduces large uncertainties
in economic model variables. Estimates "made under existing
economic and operating conditions" as defined by the
SEC (as required for "proved" reserves) generally have no significant meaning, because those conditions are
constantly changing, and our projects last for decades. The conditions
"anticipated to be commercially recovered" and "under existing economic and
operating conditions" are absolutely contradictory and nonsensical, since
anticipated means "to expect in the future". ABSOLUTELY NO
RESERVES are anticipated to be recovered in the future under existing
economic and operating conditions. The assumption that economic
and operating conditions are fixed is completely invalid. One of the main purposes of
simulation is to optimize production by determining the optimal process and
boundary (operating) conditions as a function of time (see
Goals of Reservoir Simulation).
Optimization is a pre-requisite of prediction.
The SEC rules
also state:
"(iii) Estimates of proved reserves do not include the
following:
(B) crude oil,
natural gas, and natural gas liquids, the recovery of which is subject to
reasonable doubt because of uncertainty as to geology, reservoir
characteristics, or economic factors; "
All production is subject to reasonable doubt, before
it occurs, due to guaranteed high levels of uncertainty in all of those and
many more factors.
It is virtually impossible to estimate with any
degree of certainty what will be "commercially recoverable" in the future
under unknown and unpredictable economic and operating conditions.
For example, (1) a major advance in the efficiency of alternative energy sources
could eliminate most of the value of all hydrocarbon reserves at any time.
Regulation may also do so, for example (2) the destruction of the US coal
industry by the Clean Power Plan that has reduced the value of US coal
reserves to near 0. Other examples are (3) proposed regulation of CO2
emissions (see SRMS and SPE CCUS Technical Section)
that would eliminate true reserves and hugely increase the cost of energy to
the public for no reason or benefit that can be substantiated, and (4)
regulation following the BP Macondo incident that has virtually eliminated
the value of all oil and gas reserves in federal waters, and (5) unknown
future and present values of the true rates of dollar devaluation
(inflation) resulting in misapplied "cost of
capital" and discount factor considerations. There are an infinite number of such uncertainties
that cannot be reliably predicted, unless one has or believes in psychic abilities.
The existence and incompetence of reserves definitions and reporting
requirements are certainly indications of that "Crystal Ball Syndrome".
Strictly speaking, according to the SPE/SEC rules,
the amounts and value of all defined proved, probable, and possible reserves
are and will always be exactly
0. Beyond any
reserves reporting requirements that they may rigorously satisfy, probabilistic performance
predictions are obviously required to optimize production and our
operations, and to minimize the cost of energy. As a result we have
developed some of the most complex and advanced software systems in the
world (using Pipe-it® workflow
integration and iterative optimization software applied to Sensor), which are now capable of automated probabilistic
optimization for characterization, upscaling, history matching, forecasting,
and predictive optimization - all of the components required to achieve our
goal of solving the real-time global predictive optimization problem under
uncertainty.
Simulators can predict future production, for given values of all the data, but
most of that data is usually uncertain. So we must employ
probabilistic methods to make any predictions or optimizations in reserves
estimations or in reservoir modeling, using any model making valid
assumptions while rigorously accounting for the uncertainties.
These methods, capabilities,
optimizations, and predictions are the basic components of business
management and (national) free-market competition in the energy industry
Those companies able to better plan their operations and better optimize
reserves and production to minimize risk and maximize efficiency and profit
will be more successful and others will fail, thus minimizing the cost of
energy and maximizing efficiency, technical advancement, corporate
responsibility, sustainable development, and growth of the economy (assuming
necessary and proper regulation for a sustainable national economy that is a
prerequisite of sustainable development (and of the basic sustainability of
all individuals and businesses).
Regardless of how reserves may be
defined, probabilistic analysis in reservoir modeling provides for
the most rigorous possible forecasts and (more importantly, as mainly used
historically) for probabilistic
predictive optimizations of reserves and reservoir performance. It can
also potentially eliminate or rewrite, into very simple and much more
meaningful engineering/economic and mathematical terms, the
definitions, methods, and rules for reserves estimation. |